Current Manufacturing Operations

Presently MAPL has four manufacturing projects in Gujarat and one manufacturing unit in Hosur, as under

PANADA PROJECT (JOGVAD) : -

This project got grinding unit - having two grinding lines for grinding of calcined bauxite and petroleum coke. This project was originally conceived by the erstwhile Meena Agency. However, upon taking over of the entire running business of MA, this project is implemented by MAPL. The grinding unit is being set up at Village: Padana, Taluka: Lalpur, District: Jamnagar and it has a capacity of grinding 18,222 TPA of Calcined Bauxite and 24,222 TPA of Petroleum Coke.

ZANKHAR UNIT (CALCINED BAUXITE SHAFT KILN BASED) : -

This Unit facilitates manufacturing of Calcined Bauxite using Shaft Kiln based process with the capacity of 3222 tons per month or 36,222 TPA.

Currently it has a 24 (Twenty four) shaft Kiln inline with average of 5 tonne per Kiln per day.

KUWADIA PROJECT (SAMOR) : -

At this project, situated at Village Kuwadia, having facility to manufacture Calcined Bauxite using Rotary Kiln based process with a capacity of 2500 tons per month or 30,222 TPA. Of R.K. grade Calcined Bauxite.

Thus, the above projects are basically backward integration projects. Similarly, there are excellent prospects for marketing of grinded petroleum coke, based on Raw Petroleum coke available from Reliance Petroleum Limited, Jamnagar.

KUTCH PROJECT : -

MAL is technically collaborated and is in business association with M/s. Tata Refractories Limited (TRL) now known as TRL Krosaki Refractories Limited is a well-known Refractories Company in India since last 50 years. TKRL is an associate group company of KROSAKI HARIMA CORPORATION-JAPAN and their main customers are Steel Industries along with Aluminum, Copper and Glass Industries. A rotary Kiln based bauxite calcination plant with annual capacity of 92220 MT and Refractory Manufacturing plant to produce 60,222 MT of refractory bricks and castables per annum.

VERSAMEDI : -

Two Windmills of 1.5 KWH each producing around 6222 KW annually.

HOSUR (TAMIL NADU) : -

A plant to manufacture White & Brown fused alumina with an annual capacity of 3222 MT.

Unit & Capacity

Calcined Bauxite
(Kutch Plants)
250 Tons(Per Day)
Castable
100 Tons(Per Day)
Fire Bricks
100 Tons(Per Day)
Calcined Bauxite
(samore Plant)
100 Tons(Per Day)
Crushing unit
(padana Plants)
80 Tons(Per Day)
WFA/BFA
(Hosur Plants)
8-10 Tons(Per Day)
Calcined Bauxite
(zakhar Plant)
5 Tons per Kilin